Page 12 - INDEX Summer 2024
P. 12

VICE  CHAIRMAN ’ S                                                                               VICE  CHAIRMAN ’ S


                                S AY                                                                                             S A Y  C ONTINUED . . .






          C O MMIS SIONING   –   B A CK   T O   B ASIC S ?                                                                           Test Point Locations


          There is no doubt that the building service industry has made great strides in the last few years in terms                 This leads to an associated element of functional testing and regulating systems that needs
          of achieving and maintaining improved space conditions in buildings and promoting better air quality.                      underlining. A pitot tube traverse location or the location of an orifice plate must be as detailed in
          This  progress  has  been  achieved  through  more  sophisticated  equipment  and  better  controls  and                   the relevant CIBSE commissioning code or BSRIA Guide. These provide detailed guidance on siting
          software. The result is that today’s commissioning engineers need to have at least a working knowledge                     measurement points with sufficient straight, uninterrupted ductwork or pipework up and downstream
          of some complex systems.                                                                                                   to ensure accurate readings. Any location that does not comply with the recommendations in those
                                                                                                                                     documents will, by definition, cast doubt on readings. Providing suitable locations is as much a task
          However, it is worth reminding ourselves that the basis of all of these systems is still a fan moving                      for the designer and installer as for the commissioning engineer.
          air through ductwork or a pump circulating water round pipework. For example, unless a ventilation
          system has the correct amount of air moving at the most effective speed throughout all the distribution                    Initial Readings
          ductwork, achieving the required specified conditions will be difficult, irrespective of the sophistication
          of the controls.                                                                                                           The commissioning engineer MUST record the initial total system flows and fan/pump pressures,
                                                                                                                                     ensuring in excess of 100% of the design flow rate. For traditional systems (not VAV/PICV systems),
          To that end, the CSA thinks that it is time to remind everyone of some of the basic requirements of the                    the commissioning engineer MUST record the initial indicated rates of flow at all terminals. Index
          commissioning process.                                                                                                     terminals should also be indicated on the test sheets. Any issues identified at this stage must
                                                                                                                                     be  investigated  prior  to  proceeding  with  system  regulation.  Records  of  the  initial  readings  are
          First and foremost is understanding the fan laws. There are three of them and, although usually referred                   invaluable in indicating the extent of the balancing required on the system. They may also be useful
          to as the fan laws, they also apply to pumps:                                                                              in the investigation of any problems, such as excessive noise or system resistance, experienced
                                                                                                                                     with the system once it is balanced.
              Number one:    flow rate is directly proportional to rotation speed. If the fan or pump speed is
                             increased by 10%, the amount of air or fluid moved through the system will also                         Correction Factors
                             increase by 10%.
                                                                                                                                     Ventilation system correction factors should be established, wherever possible, for each type of
              Number two:  system  pressure  is  proportional  to  the  square  of  the  rotation  speed.  That  10%                 terminal and flow capture hood in use. Where this is not possible, the commissioning engineer
                             increase in rotation speed will result in a (1.1 * 1.1) = 1.21 (that is 21%) increase in the            must agree a suitable compromise with the design team and/or witnessing agent.
                             pressure at the fan/pump discharge.
                                                                                                                                     System Reports
              Number three:  power  absorbed  is  proportional  to  the  cube  of  the  rotation  speed.  The  10%
                             increase in speed results in an increase in electrical current drawn of (1.1*1.1*1.1) =                 The  nature  and  complexity  of  some  systems  requires  a  narrative  to  describe  the  system,  the
                             1.33, or 33%.                                                                                           operating parameters, commissioning/proving process, and the reasoning behind this. An example
                                                                                                                                     would be explaining how the system diversity was set up, or filters/strainer dirty condition was
          The other basic premise of air and water systems that requires a reminder is that the current drawn by                     simulated. This report should also include a pressure profile of the Fan/AHU and pump system
          a fan or pump motor is related to the amount of air / water passed. More flow means more amperage                          pressures  including  closed  head  readings.  This  makes  it  clear  and  easier  for  the  consultant  or
          and less flow means less amperage. It is still common to encounter building services engineers that are                    witnessing authority to understand or the process to be repeated at a future stage.
          sure that if you close a fan discharge damper or pump discharge valve while it is running, the current
          drawn will rise. No, it will not. It will drop.                                                                        If commissioning engineers can reabsorb any of these basics back into their daily work ethics, the
                                                                                                                                 individuals and the projects they are involved with will benefit greatly.
          Having got those basic tenets in place, there are five further elements that the commissioning engineer
          (and designer / installer) all need to focus on:                                                                       With my other hat on, it's great to see that the success of last year's CSA Awards is heading for a
                                                                                                                                 repeat performance.
              Calibrated Instruments
                                                                                                                                 As well as our long term category sponsors Ashford Environmental Services, BSRIA, HDR, MBS Magazine,
              Whether it is a micromanometer and pitot tube being used on a ventilation system, or an electronic                 Media Control and RED Engineering, we are now joined by Banyards and Core Emirates. We are also being
              manometer being used on a heating / cooling system, the instrument must have a valid and indate                    approached by other organisations wishing to support the Awards – look out for further developments.
              calibration  certificate.  Commissioning  engineers  also  need  to  be  honest  with  themselves.  Did            Make sure you have booked your seats – and submitted your entries!
              you accidentally drop that instrument? If you did, you know it has to be checked against another
              calibrated instrument and recalibrated if necessary.                                                               You can also find this full press release in the June edition of Modern Building Services.


                                                     Keith Barker – CSA Vice Chair & Director of TTL                                                                        Keith Barker – CSA Vice Chair & Director of TTL